HGC MAC Meeting 11 September 2024

https://indico.cern.ch/event/1454139/

Pre-Production Planning (Alethea)

  • Wrapping up preseries
  • UCSB build 5 LD right for irradiation campaign
  • CMU done with pre-series
  • Waiting for hexaboards hope for Nov. Limit by ROC availability
  • Calendar
    • Nov: 2 modules /day x week (one gantry tray).
    • Dec: 4/day x week (one gantry tray)
    • Jan-Feb recieve tooling and multi-module test stands
    • March: 4 /day for 4 days
    • April: 8 /day for 4 days
    • May: 12 /day for 4 days -

(What does preproduction mean ? Could go on the detector… 3b chips.. number produced still less than the number of spares)

ESD susceptibility of Hexaboards (Fakri)

  • confirmed source of dead half chip is due to ESD damage
  • Capacitance of silicon 47 pF
  • Maybe apply a shunt during assembly?

Glue/Encapsulation studies (Chiara)

  • first a module with no epoxy on the perimeter has been built and thermal cycled
  • All the modules built with the new glue/tape pattern do not show noisy channels identified during assembling procedure
  • Covering CM capacitor with encapsulate helps protecting chips against failures - This should be done before getting hexaboard to MACs since is time consuming

Engineering update (Suzzane)

  • US MAC Assembly tooling order: Xometry ~16 days
  • (Asia MACs Xometry also ?)

Had to leave. requested recording.

Laminated Baseplate Pre-Production (Markus)

  • Stresses minimal for Titanium
  • Baseplate production needs to stay ahead of MAC pre-production ramp up schedule

Local Database Ecosystem (Sindhu)

  • Nice introduction… Need to watch video

TTU MAC Updates

  • Assembled another pre-series module: BP-Si: Transfer Tape Si-Hex: Hybrid Tape
  • IV breakdown at 400V
  • Exercising local and global databases

Follow-ups